Floor Framing Lumber

Day #40

August 30, 2018 – Today Lowe’s delivered the balance of the floor framing lumber. The delivery included the remaining ledger boards, edge beams, rim joists and all the porch addition floor joists. 

Even though the delivery was rather late, after the lumber arrived I started installing the first section of the porch floor joists. At the end of the day I had about 8 or 9 joists in place. Tomorrow will be more of the same, porch addition floor joists.

Sadly, I broke the handle of my favorite framing hammer. This is the same hammer I used to build my house.

Hopefully I will find a good replacement.

Floor Framing Lumber - Lowe's Delivery
Lowe’s truck leaving after the floor framing lumber delivery.
Floor Framing Lumber
The porch floor framing lumber pile.
Floor Framing Lumber - Porch Floor Joists
Framing the 1st section of porch addition floor joists.
Broken Hammer
I broke the handle of my favorite framing hammer!
Floor Framing Lumber - Porch Floor Joists
Near the end of the day.

Kitchen Floor Framing Complete

Day #38

August 18, 2018 – After a quick trip for lumber, some sawing and hammering, and voila, kitchen floor framing complete! The addition is now starting to take shape.

So far I am am very happy with the concrete work. Although the pictures are deceiving and the framing is not conventional the floor is perfectly level. It should also meet the existing floor elevation once we finish it off.

We also managed to get some more of the limestone spread in the area under the porch addition. 3/4 of the way done! Once we have the sub-grade stone complete I will begin the porch floor framing.

Kitchen Floor Framing
Kitchen addition floor framing continues.
Kitchen Addition - Floor Joists
Kitchen addition floor joists in progress.
Kitchen Addition - Floor Joists
All but one of the kitchen addition joists are set.
Kitchen Addition - Solid Bridging
Solid 2 × 10 bridging at the kitchen addition.
Kitchen & Porch Addition Overview
Elevated shot of the kitchen floor framing and the stone under the porch addition.

Landscape Fabric

Landscape Fabric

Day #36

August 12, 2018 – To dress up the area under the kitchen and porch addition we placed landscape fabric. On top of this will go 2″ of limestone. This will serve to keep us out of the mud while framing.  It will also keep the weeds from growing under the porch in the future.

With the landscape fabric in placed I continued floor framing with a ledger board under the living room door. The new ledger boards are secured by drilling completely through the existing oak beams. They are bolted from the underside of the cottage with hot dipped galvanized bolts. It’s a little freaky crawling under the cottage. The dreaded Polyphemus moth caterpillar, spiders, hellgrammites,  black snakes, copper heads…….I did smell cucumbers!

Late afternoon we got everything all cleaned up and ready for next weekends stone delivery. Plus we did a sneak peek review of the new siding and roof colors. There will be more on that selection later. Stay tuned….

Landscape Fabric
Sub-grade preparation with landscape fabirc.
Ledger Board - Living Room Door
Ledger board under living room door.
Under Cottage - HDG Bolts
Hot dipped galvanized bolts underneath the cottage.
Under Cottage - HDG Bolts
Hot dipped galvanized bolts underneath the cottage.
Polyphemus Moth Caterpillar
Polyphemus Moth Caterpillar
Ledger Board - Living Room Door
Ledger board under living room door.
Ledger Board - Along Living Room
Ledger board along the living room.
Sub-grape Prep / Floor Framing
Sub-grade landscape fabric prep and floor framing.
Siding & Roofing Colors
Color samples for the new siding and roofing.

Kitchen Floor Framing Continues

Day #34

August 5, 2018 – The kitchen floor framing continued today. The heat index was 102 degrees but it was so humid that the puddles were not even drying up.  I was taking it very slowly.

The existing Cot-Taj-Mahal is built on rough cut 2″ × 6″ solid oak beams. I didn’t want to place a lot of  additional load on the  structure so we poured a line of footers and piers as close to the existing wall as we could. As a result, along the kitchen, I have to transition from a 6″ beam to an 8″ ledger and then to a new 10′” beam. As expected, nothing is square. Gotta love 65 year old structures! 

Before I can go any further with the ledger board installation I need to demo part of the frost wall under the living room door. I’m hoping I can cut it with a concrete saw.

Floor Framing - Kitchen Addition 02
Overview of the floor framing at the new kitchen addition.
Floor Framing - Transition Joists 01
Here we transition from a 2 by 6 beam to a 2 by 10 beam. We have 2 by 8 joists in between.
Floor Framing - Transition Joists 02
We have 2 by 8 joists in between.
Floor Framing - Kitchen Addition 01
Parking lot view of the floor framing at the new kitchen addition.

Floor Framing New Kitchen Addition

Day #33

August 4, 2018 – This morning we made a run out to the Lewistown Lowe’s for treated lumber to start the floor framing.  Yesterday I did a quick takeoff for the lumber I needed to start the floor framing along the kitchen addition. I was anxious to get started with the ledger boards while I had help. Unfortunately when we got back we discovered that the power was out. Son of a bitch!

I called in the power outage to Pennelec. After a short time they returned the call with a status update. It was anticipated that the power would come back on by 1:30 PM. My help could only stay until ,noon so that pretty much shot a hole in my plans!

With the power out I decided to strip the last pier manually with an old time screwdriver and a ratchet. I had to bail the hole out several times but I got it stripped and backfilled. 

At 1:05 PM the power came back on. Ahead of schedule, imagine that. The rest of the afternoon I managed to get a small portion of the floor framing completed along the kitchen addition.

Tomorrow, if the power stays on, I’ll continue the kitchen addition floor framing.

Ratchet Work
Taking apart the last pier form with no electricity.
Last Concrete Pier
The forms from the last concrete pier are stripped.
Floor Framing - Treated Lumber
This was our first load of treated lumber for the floor framing.
Floor Framing - Ledger Board
The first ledger board for the new kitchen floor.
Floor Framing - Ledger Board
Ledger boards for the new kitchen floor.
Floor Framing - Ledger & Beam
Ledger boards, band joist and beam at the new kitchen floor.
Floor Framing - Band Joist
The first band joist and beam for the new kitchen floor.

Muddy Mess Again

Day #32

August 3, 2018 – Got to the Cot-Taj-Mahal around mid-day.  The backyard was flooded, the side yard was flooded and the front yard was flooded. Once again, the rain from the previous week left a muddy mess.

The last concrete pier was filled to the brim with ground water. There were three of four frogs sunbathing along the edge. When I approached they all dove in for a swim.

After exposing some more of the existing floor beams along the kitchen, I decided to just chill out and enjoy the day without slopping around in the muddy mess.

Later in the evening, I had dinner and a few drinks at Wingman Brew N Que. That seems to be our new Friday night haunt. I tried a new beer, Field Trip Series Pineapple Mango by Short Bus Brew House from McClure, Pa. It was pretty good.

On the way back to the cottage I made a stop at Angelo’s Italian Restaurant. Chris who works there makes wonderful Whoopie Pies in all sorts of flavors. He gave me a a few of his new Blueberry-Banana to take with me and that was it for the day.

Muddy Mess
Rain, rain go away, please come back another day!
Muddy Mess - Last Concrete Pier
The last concrete pier filled with ground water.
Existing Floor Beams
Solid Oak double 2 inch by 6 inch rough cut floor beams with 1 inch rough cut floor planking.