Entry Door Rough Opening

Day #91

August 24, 2019 – Before the roof framing can continue, we must repair the front wall along the length of the living room. The majority of this wall is rotted out from years of water leaking through the old porch roof. We’ve been working on this for several weekends but I think we are nearing the end of the rotted section. After framing the rough opening for the new entry door, and removing living room window, I think we will have all the rotted wood repaired.

This morning I started removing the siding and oak planking around the front door. I removed the screen door, the front door and the door frame. The door frame came out in one piece. We will be able to re-use it, temporarily, while we wait on the delivery of the new door.

Front Door Demo
Screen door, front door and frame removed.
Front Door Frame
The front door frame in one piece.

I hit another big section of rotted oak planking next to the living room window. This was the end of the old porch. Basically, in this area, any water that hit the old porch roof was rolling backward into the exterior wall. It’s a mess!

Rotted Wood
Hopefully the last section of rotted wood.
Rotted Wood Planking
Close up of the rotted oak planking near the living room window.

Rough Opening

Near the end of the day I got the rough opening studs, header and jack studs put together and installed in the opening. The new entry door rough opening is 72″×80″. To re-use the old door and frame I had to increase the opening height three inches to 83″. Once I have the new entry door I can block the opening down to 80″ so that it fits.

Entry Door Rough Opening
Entry door rough opening framing in progress.

Before we left for dinner we installed a “snake tarp” across the opening. Thankfully there is no rain in the forecast this evening. We are hoping that the “snake tarp” keeps the snakes that live under the cottage from coming in. Tomorrow I will re-install the old door and close up the opening for the week.

Snake Tarp - Entry Door Rough Opening
Entry door rough opening covered with a “Snake Tarp” for the night.

Before dinner we stopped at Lowe’s in Lewistown and placed the order for the new sliding entry door. We purchased a Pella 350 Series Vinyl Sliding Patio Door. Delivery will take 3 to 4 weeks. It’s very exciting!

Tomorrow I will re-install the old door frame, door and screen door and temporarily close in the remainder of the opening while we wait on the delivery of the new door.

Leave a Reply

Your email address will not be published. Required fields are marked *