Preparation for Footing Concrete

Day #20

July 6, 2018 – I was up early and out to purchase reinforcing bars to place in the footers in preparation for the concrete pour.

Wolfley Excavation was on site early this morning to continue spreading stone for the new expanded parking area. He was able to get 4 more loads delivered and spread before the quarry closed. It’s looking pretty good. The concrete truck should have no problems getting in and turned around.

At noon I confirmed the delivery of 2.75 cubic yards of 3000 psi  concrete with Juniata Concrete out of Mifflintown for tomorrow at 7:00 AM.

Tied up and placed rebar all afternoon waiting on my help to show up. Left the footers uncovered all night to try and dry them out a bit.

Preparation looks good. Big day tomorrow!

Stone Truck - Preparation For Concrete
First stone delivery this morning.
Stone Truck - Wolfley Excavation
Stone delivery for expanded parking lot.

Excavating Footings

Day #19

July 5, 2018 – Today was a good day. Wolfley Excavating was back on site to spread stone for an expanded parking area. They managed to get three loads of 2A limestone delivered and spread before the quarry closed for the day

Around 3:30 PM they dropped the bucket on the skid loader and hooked up a 24″ diameter auger. With the auger attached they began excavating the footings.  In a little over 2 hours they completed the remaining 16 footings. 

The drilling went much better than I had expected. There were not too many roots but there was more river rock underneath the living room door. This caused the auger to jump off the marked. We will have to hand dig to correct the location. 

The front yard now looks like a mine field.

Tomorrow we will begin the installation of reinforcing bars in preparation for the concrete pour.

Once again there was a threat of a pop up rain storm. As a precaution we covered all nineteen of the footings.  Thankx to Grammy and Fannie for buying 700 traps off of the clearance rack.

2A Limestone
First load of 2A limestone arrives on site.
Expanded Parking Area
Spread stone in the expanded parking area.
Skid Loader & 24" Auger
Skid loader with 24″ auger attachment digging 3ft deep footers.
Excavating Footer At Living Room Door
Footer excavation under the living room door.

https://www.instagram.com/p/BlBXTCbgnO8/?taken-by=jcrowleyjr

Front Yard Mine Field
After the footers were dug the front yard looked like a mine field.

Hand Dug Footings

Day #18

July 4, 2018 – Today was the start of the footing excavation. We hand dug the first three footers 2′-6″ × 2′-6″ × 3′ deep. Two of them are in close proximity to the underground plumbing. One footing is close to an existing pier that is slightly tilted. We did not want to risk damage to the plumbing or the tilted pier from the digging auger. 

All of the old wood from the porch roof was relocated.  It was moved from the front of the cottage and put in a neat stack by the old shed. We took the rotted picnic table over to the fire pit. There it will await the return of the #arsonsquad.

We turned over the old wooden platform that the picnic table sits on.  After a brief inspection we decided it is in great shape. There is no rot at all, so we relocated it close to the fire pit. It will serve as a stage for future nonsense.

It rained for several hours jeopardizing tomorrows planned parking lot installation. Hopefully Wolfley’s Excavating & Septic Pumping will be on site tomorrow to get it started.

Luckily we had covered the footers prior to the storm. Hopefully the covers will keep them from filling with water so that they can be prepped for the concrete pour.

Hand Dug Footing #1
Hand dug footing between underground plumbing lines.
Hand Dug Footing #2
Hand dug footing near the existing tilted pier.
Covered Footing Excavation
Three hand dug footings covered before the rain storm.

Footing Layout Day

Day #17

July 1, 2018 – Today was footing layout day. I cut my footer guide from a sheet of plywood and laid out all nineteen footers. All locations are marked with orange marking paint.

We are ready to dig!

At the end of the day, sitting in the front yard with a cold beer, looking over my surveying work, I realized that I made a 6 inch error in the layout. Dam it…! More stuff to worry about! Anyway, here’s what it looks like.

Footer Layout
19 footers laid out and marked with marking paint. Ready to dig.

Backfill & Batter Boards

Day #16

June 30, 2018 – Before I could put up the batter boards I needed to backfill the plumbing trenches.

After I put up the boards I pulled some string lines off of the existing cottage walls. I determined that the cottage is officially 4 1/2 inches out of square. We had to expect that after almost 70 years in the damp river environment. Well, as Troy says, “We gotta build to what’s there.” So on with the show!

With the string lines in place we can proceed with the footer layout.

Plumbing Backfill
Plumbing sanitary and drain lines backfilled and marked with marking paint.
Batter Boards
Batter boards installed and string lines pulled for the footer layout.