Day #19

July 5, 2018 – Today was a good day. Wolfley Excavating was back on site to spread stone for an expanded parking area. They managed to get three loads of 2A limestone delivered and spread before the quarry closed for the day

Around 3:30 PM they dropped the bucket on the skid loader and hooked up a 24″ diameter auger. With the auger attached they began excavating the footings.  In a little over 2 hours they completed the remaining 16 footings. 

The drilling went much better than I had expected. There were not too many roots but there was more river rock underneath the living room door. This caused the auger to jump off the marked. We will have to hand dig to correct the location. 

The front yard now looks like a mine field.

Tomorrow we will begin the installation of reinforcing bars in preparation for the concrete pour.

Once again there was a threat of a pop up rain storm. As a precaution we covered all nineteen of the footings.  Thankx to Grammy and Fannie for buying 700 traps off of the clearance rack.

2A Limestone
First load of 2A limestone arrives on site.
Expanded Parking Area
Spread stone in the expanded parking area.
Skid Loader & 24" Auger
Skid loader with 24″ auger attachment digging 3ft deep footers.
Excavating Footer At Living Room Door
Footer excavation under the living room door.

 

Front Yard Mine Field
After the footers were dug the front yard looked like a mine field.