Day #18
July 4, 2018 – Today was the start of the footing excavation. We hand dug the first three footers 2′-6″ × 2′-6″ × 3′ deep. Two of them are in close proximity to the underground plumbing. One footing is close to an existing pier that is slightly tilted. We did not want to risk damage to the plumbing or the tilted pier from the digging auger.
All of the old wood from the porch roof was relocated. It was moved from the front of the cottage and put in a neat stack by the old shed. We took the rotted picnic table over to the fire pit. There it will await the return of the #arsonsquad.
We turned over the old wooden platform that the picnic table sits on. After a brief inspection we decided it is in great shape. There is no rot at all, so we relocated it close to the fire pit. It will serve as a stage for future nonsense.
It rained for several hours jeopardizing tomorrows planned parking lot installation. Hopefully Wolfley’s Excavating & Septic Pumping will be on site tomorrow to get it started.
Luckily we had covered the footers prior to the storm. Hopefully the covers will keep them from filling with water so that they can be prepped for the concrete pour.