Day #8
June 2, 2018 – Today I dug up the sewer piping from the bathroom and discovered that the 4 inch elbow coming from the toilet waste had a crack in it. Also discovered that the bathroom sink is on it own 4 inch drain lateral.
I was hoping that the sink drain and toilet waste piping came together somewhere but that was not the case. I dug out from the cottage 12 feet and they did not meet up.
Rather than dig all the way to the septic tank we’ll install new 4 inch schedule 40 pvc piping and tying them together outside the edge of what will be the new porch foundation. I hope that this will hold up well into the future.



Tomorrow we will have to make a trip to Lowe’s for sewer piping supplies.