Gable End Framing & Plywood Sheathing

Day #71

June 28, 2019 – Continuing the dry in process I completed the gable end framing and plywood sheathing. This closes in the end wall of the new kitchen space.

Gable End Framing
Gable end at the new kitchen addition side.
Gable End Framing
Gable end framing in progress on the new kitchen addition side.
Plywood Sheathing
Installation of plywood sheathing on the gable end of the new kitchen addition.
Plywood Sheathing
Plywood sheathing completed at the gable end.
Plywood Sheathing
Completed plywood sheathing under the rake.

With the gable end framing completed, tomorrow I plan on installing two more porch roof rafters on the living room side. This will give me a total run of 16 feet of roof to close in. This makes it a lot easier when estimating and purchasing roof sheathing and felt paper. Once I complete these rafters and a little bit of miscellaneous roof framing we will be ready for roof sheathing.

Once again I got cleaned up and went to Angelo’s Restaurant for dinner. Tonight I had one of their Super Salads with grilled shrimp. The salad was good. They have a awesome house dressing!