Barn Siding Installation Continued

Day #203

February 24, 2021 – I made a trip to Lowe’s in Mechanicsburg to pick up a load of pine barn siding and Shiplap paneling and then it was off to the cottage. Today I will continue the barn siding installation in the kitchen. I hope to complete this ceiling work today.

Barn Siding & Shiplap Paneling

When I got to the cottage I saw a strange set of prints in the snow. I don’t know if it was a rabbit or what. I made a mental note to see if I could figure it out later.

Snow Tracks
Strange tracks in the snow.

To complete the barn siding on the ceiling in the kitchen I had to first relocate the temporary electric wires. I cut them loose from the ceiling joists and re-attached them to the top of the pantry and utility closet (Chokey). I bridged this space with a piece of furring strip.

Temporary Electric & Barn Siding Installation
Temporary electric wires attached to ceiling joists.
Barn Siding & Re-located Electric
Temporary electric wires re-located.

With the electrical wires re-located the barn siding installation continued and I quickly reached the peak of the ceiling.

Barn siding installed to the kitchen ceiling peak.

Here are a couple photographs of the completed barn siding installation at the kitchen ceiling. I will install a center beam to cover and finish off the openings at the peak. We are going to purchase some reclaimed “Worm Wood” for this beam.

The cottage and the river are beautiful in the winter especially with a nice covering of snow.

Later in the afternoon I walked down to the Boob Tree to see how Karen, With the Good Arm was making out. She was all snug in her Boob Tree cavity just like we left her. I hope she keeps a good eye open for high water in the Spring.

Walk to the Boob Tree
Karen with the Good Arm
Karen with the Good Arm

Barn Siding Continued

Day #200

February 13, 2021 – I’m back today to continue the barn siding installation on the new kitchen ceiling. Picking up where I left off yesterday I moved up towards the peak of the ceiling.

The railroad side went a bit slower. I installed over the utility closet, a.k.a. the Chokey, and the newly framed pantry closet. After clearing these obstacles I had to contend with the temporary electrical wiring. Hindsight says I should have installed the barn siding prior to the pantry and Chokey framing. Oh well…

It was way to cold to spend the night so I headed back home at the end of the day.

Barn Siding Installation

Day #199

February 12, 2021 – I started the tongue and groove barn siding installation in the new kitchen today. I purchased the first batch at the Lowe’s in Mechanicsburg. Thankfully the highways were dry as I hauled it to the cottage.

The ground was snow covered and it was a whooping 26°F inside the cottage when I got there. Freezing my ass off! I got the little electric heaters going right away.

Once I had the barn siding inside I started the installation in the kitchen, along the river side. It went pretty well. I made it up past the light fixture junction boxes. It looks awesome!

Working off a ladder I know that this barn siding installation is going to take a couple of days. I’m here for the weekend so we’ll see how far I get.